What is a key indicator that bottleneck capacity is adequate for a given schedule?

  1. The production costs are minimized

  2. Customer satisfaction is maximized

  3. Data from previous schedules align

  4. Resource utilization rate is optimized

The correct answer is: Resource utilization rate is optimized

The choice indicating that the resource utilization rate is optimized is correct because it reflects the effective use of available capacity within the production environment. When bottleneck capacity is adequate for a given schedule, it means that the critical resources that may limit production output are being used at an optimal level without excessive idle time or overloading. Optimized resource utilization ensures that production is flowing smoothly through the bottleneck, maximizing output while balancing the workload across resources. This strategic management of bottlenecks directly contributes to meeting production schedules without delays, thus confirming that the capacity aligns with the demand requirements. The other choices relate to production efficiency and output but do not specifically indicate the adequacy of bottleneck capacity in the same direct manner. For instance, while minimizing production costs and maximizing customer satisfaction are important, they do not necessarily provide direct insights into whether the bottleneck is adequately addressed for the specific scheduling needs. Similarly, while alignment of data from previous schedules can provide useful historical insights, it does not ensure that current resource constraints are addressed effectively.